Comment on Freelancing (?) programmers here: How do you estimate how many scrum points a specific project will require? Is there a template?

footfaults@hexbear.net ⁨6⁩ ⁨months⁩ ago

Story points are unique to the team that is doing the work. Basically, a 21 point story for me could be a 3 point story for you.

In of themselves, the points are not important. Just size the stories to some amount of points that is reasonable and then do a sprint. The objective is to get a sense of how much work can be done in a sprint, to help create forecasts of when work will be completed.

source
Sort:hotnewtop